Date
Action
06/09/2006 Update
06/08/2006 Update
06/07/2006 Update
06/06/2006 11:00 Go-Live!
06/05/2006 Go Live will be June 6, 2006 with the EOC switching first and the remote sites following.
05/25/2006 Tentative Go-Live Date of June 5 set.
04/21/2006 Status Update
03/13/2006 CAD "Go-Live" date postponed.
02/22/2006 Remote Site Update. Click here to read
02/16/2006 Status Update. Click here to read.
02/08/2006 Status Update. Click here to read.  Remote Site Update. Click Here to read.
01/23/2006 Remainder of remote site equipment delivered.
04/11/2005 Upgrade to version 7.9.3 - Third Map Roll from ESRI server to CAD.
02/07/2005 Go-Live Date delayed.
01/17/2005 Installation of one CAD workstation at each of 14 remote dispatch locations.
01/03/2005 Remote site train-the-trainer training started.
12/20/2004 Upgrade to version 7.9.2 - Second Map Roll from ESRI Server to CAD
09/20/2004 5 Day Train-the-Trainer II Class
09/14/2004 Date confirmed to move "Go Live" date to March 14, 2005
09/13/2004 5 Day System Administrators II class.
08/30/2004 5 Train-the-Trainer I Class
08/30/2004 First map roll from ESRI ARCGIS Server to CAD.
08/16/2004 5 Day "Supporting Cad" Class - Windows 2003 Server
0714/2004 Decision made to move "Go Live" date to week of November 29, 2004.
07/12/2004 Install networking equipment at backup EOC and 14 remote dispatch locations. 
07/12/2004 5 Day System Administrators I class to start the process of "fine tuning" the system.
06/02/2004 3 Day CADDBM class for review and initial load of system tables.
06/01/2004 Deadline for major database updates to current CAD system.
05/20/2004 Review of CAD Database prior to transfer into new system
05/17/2004 Servers and initial workstations arrive and are installed.
05/12/2004 Networking equipment arrives. Start to install cabling at EOC.
05/06/2004 Hardware started to arrive at EOC.
04/22/2004 Verizon completed installation of T1 phone circuits to 14 remote dispatch locations.
04/21/2004 Demo of Intergraph Public Safety  I/Leads RMS system to Police Chiefs Radio Committee.
04/07/2004 Existing CAD System operational change for existing remote site users.
04/05/2004 Mobile data access to the new CAD system. ( Minimum Specs for mobile computers )
03/29/2004 Week long staff seminar on system configuration, database and map definition.
03/10/2004 Networking review and remote site visitations.
0305/2004 Letter Mailed to formerly self-dispatched police departments.
03/05/2004 Project kick off meeting. Initial phases of project discussed and planned.
02/27/2004 Letter mailed to self-dispatched police departments.
02/19/2004 Contract signed by all parties. Project kick off meeting scheduled for 3/5/2004
01/15/2004 Resolution signed to enter into Contract negotiations with Intergraph Public Safety. (IPS)